26 July → 20 August 2021
Construction work commenced on bus stops. We will be back to complete these.
September 2021
Engagement with Businesses and the Community begins
21 September 2021
Webinars for Businesses and Residents
30 September 2021
Deadline for Business Loading Survey Reponses
December 2021
Designs Developed, including Road Safety Audit and EQIA report
05 January 2022
Statutory Consultation period which ends on 26th January 2022
15 January 2022
In person event at The Qube. PLEASE NOTE, THIS EVENT IS NOW CANCELLED
18 January 2022
Online webinar 6:00-7:30pm
See Update (News Feed) section of the project page for detail on how to join.
01 March 2022
Advanced publication of the report
11 March 2022
Decision about implementation published
18 March 2022
Confirmation of decision made (to implement the project)
May 2022
Construction begins
30 September 2022
Anticipated works completion date