Project timeline
April 2015
First engagement exhibitions
First engagement exhibitions
where the community shared their ideas on early concepts.
July 2016
Public consultation began
Twelve weeks of public consultation was launched, including a three day exhibition of the detailed designs.
January 2018
Designs revised
Detailed design work on the project considering feedback from previous engagement. Changes made include additional loading bays, improved links to the existing cycle network, an increased number of crossing facilities in Hertford Road.
03 April 2019
Statutory consultation commences
Launch of statutory consultation relating to the traffic orders for the A1010 North and public exhibition to show the changes to the design following the initial consultation/ community co-design workshops.
10 April 2019
Public exhibition of plans
From 3pm - 8pm at the Albany Leisure Centre you are invited to attend the public exhibition of the A1010 North drawings. Our design team will be there to answer questions and you may complete the consultation survey there.