29 June 2020 Update

The Council has submitted a number of funding bids to Transport for London and the Department for Transport over the last two months. We have received confirmation that 5 of our bids have been successful. Work on the following schemes will be proceeding:

  • Completion of the A1010 North project
  • Link from the A1010 South with North Middlesex Hospital and into Haringey
  • Implementation of 12 School Streets
  • Angel Walk Edmonton walking and cycling project
  • Bowes Primary Area Quieter Neighbourhood scheme

In addition, the Council are currently awaiting approval of funding for a further 9 schemes.

More details on the status of each scheme can be viewed in the Document Library.