Construction update July 2024

The works along the New River as part of the Enfield town to Broxbourne Walking and Cycling Route commenced on Tuesday 7 May 2024 and have been progressing well. The off-road section has been split into multiple phases and consists of the construction of a shared use path running for 2.9km adjacent to the New River. 

The works are anticipated to be completed by the end of the year. Pedestrian access will be restricted throughout the works. Advanced warning signage will be placed at strategic locations to effectively advise and guide the public. We apologise for any inconvenience these restrictions may cause.


Works currently underway

Phase 1 of the works between Tenniswood and Catherhatch have been progressing well and are due to be completed at the end of July. The new shared use path will be constructed; however, this section will remain closed until the planting along the path can be completed. The planting is scheduled at the end of summer when the weather is better suited to allow for the best chance of plant survival.


Upcoming works

The next phases of construction of the route are outlined below. The order that these phases will be delivered in is subject to change. The upcoming phases of construction are:

Phase 2 - Carterhatch Lane to Goat Lane: The second phase of the off-road section between Carterhatch Lane and Goat Lane is due to start this week and will take approximately 6 to 8 weeks to complete. Throughout the construction of Phase 2, the contractor will need to continue to temporarily occupy the section of the road on Carterhatch Lane bridge using cones and barriers which are currently in place.

Phase 3 - Goat Lane to Turkey Brook: The third phase will include the installation of a new bridge across Turkey Brook. Parking restrictions will be in place on Worcesters Avenue to allow for a welfare unit / site stores and access to the New River.

Phase 4 - Turkey Street to Bullsmoor Lane: Parking restrictions will be in place on Bullsmoor Lane to allow for a welfare unit / site stores and access to the New River.

Phase 5 - Turkey Brook to Turkey Street: The shared path is proposed to continue along the New River adjacent to St Ignatius College.

Phase 6 - Bullsmoor Lane to the M25: The final phase will connect the route from Enfield over the M25 to the existing Broxbourne shared path, creating a continuous walking and cycling route between Enfield Town and Broxbourne. Parking restrictions will be in place on Bullsmoor Lane to allow for a welfare unit / site stores and access to the New River.

When will the work be completed?

The path along the New River is due to be completed by the end of the year, with the project continuing into mid-2025 as we complete some of the on-road works. Please note the schedule is subject to change due to weather or other unforeseen circumstances.

If you have any queries relating to the construction works, please contact our contractor Kenson Highways at PLO@KensonHighways.com.

More information

As we progress through each phase of construction, updates will be posted on this project page.

We understand that construction works of this nature can cause some disruption and we apologise for any inconvenience caused. We and our contractor work hard to ensure that disruption is minimised where possible whilst the works are undertaken.

To view the designs and for more information, please see document library on the right hand side of this project page.

Should you have any general queries about the project, please contact the Journeys and Places team at JourneysandPlaces@enfield.gov.uk.

Share Construction update July 2024 on Facebook Share Construction update July 2024 on Twitter Share Construction update July 2024 on Linkedin Email Construction update July 2024 link
<span class="translation_missing" title="translation missing: en.projects.blog_posts.show.load_comment_text">Load Comment Text</span>