Construction update November 2024
Works currently underway
We have now completed most of the work for the walking and cycling path between Tenniswood Road and Goat Lane, and between Turkey Street and Bullsmoor Lane. We will begin installing the last elements throughout these sections in the lead up to the new year including fencing, lighting, planting, seating, and cycle stands.
The new walking and cycling parallel crossing on Carterhatch Lane is also underway and expected to be completed in mid-December.
Upcoming works
Construction is scheduled to start this week on the section between Bullsmoor Lane and the M25. We will be constructing the path along the eastern side of the New River in conjunction with temporary remedial works on the western side of the New River. This will allow for continued access to other sections of the path in the meantime. The existing site compound on the southern side of Bullsmoor Lane will be relocated to the northern side, this will enable the storage of material and equipment while this section is being constructed. Two-way traffic flow will continue throughout construction, apart from during short periods where stop-go signs will be used during deliveries.
We are still expected to open the new walking and cycling path connecting Enfield Town to Broxbourne in early- mid 2025. We appreciate your continued patience during these final phases of construction.
If you have any queries relating to the construction works, please contact our contractor Kenson Highways at PLO@KensonHighways.com.