Why has the project divided in phases?

    The project has been divided into phases to streamline implementation and align with budget constraints. This staged approach guarantees effective execution of each step and allows for better resource allocation. It also makes it possible to respond promptly to variations in funding, which promotes flexibility all the way through the project lifecycle.

    What are the sections of the route?

    The route has been broken up into sections as follows:

    • Section 1: Tenniswood Road/Ladysmith Road link
    • Section 2: Donkey Lane/Cambridge Gardens link
    • Great Cambridge Road crossing (this section is being progressed by TfL)
    • Section 3: Brick Lane cycling improvements
    • Section 4: Brick Lane walking improvements
    • Section 5: A1010 Hertford Road junction



    What is a continuous footway?

    Continuous footways are extensions of pavements across the carriageway of a side street at its intersection with another road. This provides an uninterrupted route for pedestrians and cyclists to cross these side streets and helps reduce vehicle speeds upon the approach to junctions where continuous footways are installed. Continuous footways also improve visibility while reducing the carriageway width and increasing pedestrian space.

    Why is the footway parking being removed?

    The council’s approach is to remove any existing footway parking that hinders active travel aspirations. There are ample potential spaces in the area, and drivers can find alternative kerbside positions slightly further away.

    What does the current community engagement cover?

    The January engagement consists of a Statutory Consultation on Phase 1 of the project and additional questions relating to Phase 2, which will be subject to funding and further statutory consultation.The community engagement will run from 17th December to 11th February. 


    What are the timelines for the project?

    Information about key project dates can be found in the Key Dates section on the right-hand side of the project page.

    Our timeline to the end of financial year 2023/24 is as follows: 

    • Community engagement, including webinar and drop-in session – 17 January 2024 to 11 December 2024
    • Commence construction of Section 1 - March 2024

    Further progression of the scheme beyond the current financial year will be subject to funding.


    What interventions are being proposed as part of the Section 1: Tenniswood Road/Ladysmith Road link

    The following interventions are proposed for this section of the route:

    • Upgraded and widened shared path 
    • Amended ramp to accommodate cyclists and surface improvement
    • Handrail installation at the stairs
    • New stop and rest area 

     

    You can view the plans for this section in the Document library.

    What interventions are being proposed as part of the Section 2: Donkey Lane/Cambridge Gardens link

    The following interventions are proposed for this section of the route:

    • Introduction of a buildout at Ladysmith Road at the entrance to Soldiers Alley to facilitate cycle transitions on/off carriageway and increase visibility for pedestrians and cyclists
    • Introduction of cycle road markings
    • Current staggered barriers along Soldiers Alley will be replaced with bollards
    • Cycle track delineated in car park to guide cyclists and ensure drivers are aware of proposed cycle route
    • Create a cycle bypass at height gate at Donkey Lane
    • Reconfiguration of existing barriers to improve accessibility for all users.

     

    You can view the plans for this section in the Document library.


    What interventions are being proposed as part of the A10 Great Cambridge Road crossing

    This section is being progressed by TfL.

    What interventions are being proposed as part of the Section 3: Brick Lane cycling improvements

    The following interventions are proposed for this section of the route:

    • Introduction of a buildout on Oldbury Road to facilitate cycle transitions on/off carriageway and increase visibility for pedestrians and cyclists
    • Introduction of cycle markings
    • Conversion of existing speed hump to cycle friendly sinusoidal humps
    • Introduction of a buildout with a rain garden and cycle parking outside of the school pedestrian entrance that will act as traffic calming.
    • Introduction of an informal crossing outside school and a buildout with a rain garden that will act as traffic calming.

     

    You can view the plans for this section in the Document library.



    What interventions are being proposed as part of the Section 4: Brick Lane walking improvements

    The following interventions are proposed for this section of the route:

    • Introduction of continuous footway on Gough Road, Wolsey Road, Baranard Road, Orchadleigh Avenue, Yeomans Way and Cuba drive to improve pedestrian level of service and reduce the speed of turning vehicles
    • Tightening of the junction on Hammond Road and Mapleton Road to improve the pedestrian level of service and reduce the speed of turning vehicles.
    • Removing the footway parking at the junctions

     

    You can view the plans for this section in the Document library

    What interventions are being proposed as part of the Section 5: A1010 Hertford Road junction

    The following interventions are proposed for this section of the route:

    • Tightening of the junction of Hertford Road with Brick Lane to reduce vehicle turning speeds
    • Introduction of contraflow cycling at the service road on the west side of Hertford Road
    • Tightening of the south side of the service road junction
    • Introduction of short section of two-way cycle track for safe cycle access to and from Hertford Road at its junction with Brick Lane.
    • Relocation of the service road exit on the west side of Hertford Road.
    • Removing approximately four parking spaces on the service road on the west side of Hertford Road


    You can view the plans for this section in the Document library.