Construction of Sterling Way Crossing commencing soon

From 26 January 2026, Transport for London in partnership with Enfield Council will start works on the Sterling Way Crossing. This new crossing will make it easier and safer to walk, cross and cycle on Sterling Way near its junction with College Close and Silver Street Overground station. It is being delivered as part of the Shaping Edmonton programme. The construction works will:

  • Replace the temporary barriers in the central reservation on Sterling Way with a new pedestrian island and staggered crossing, making it easier and safer for people to cross.
  • Create a new two-way cycle link between the crossing and the College Close junction to enhance cyclist safety along Sterling Way.
  • Introduce dedicated bays for loading, rapid electric vehicle charging and disabled parking outside no.18 to 38 Sterling Way.

The works will be undertaken under single lane restrictions from Monday to Friday, 08:00 – 17:00, and on Saturdays from 08:00 – 14:00 between January and July 2026. However, temporary traffic signals and road closures will be required during some phases of the work as detailed in the table below.

Dates & times

What we are doing

How this may affect you

13 – 16 March between 21:00 – 05:00

Footway works and buildout eastbound on Sterling Way.


Temporary two-way traffic signals on Sterling Way near its junction with College Road.


2 – 9 June between 21:00 – 05:00


Footway works and buildout westbound on Sterling Way.


Temporary two-way traffic signals on Sterling Way near its junction with College Road.


29 June – 4 July between 21:00 – 05:00


Carriageway resurfacing on Sterling Way, between its junctions with Fore Street and Silver Street / Victoria Road.


Sterling Way closed in both directions between its junctions with Fore Street and Silver Street / Victoria Road.

Access to and from College Road via Sterling Way will be restricted.


Parking

Parking bays will be suspended from 26 January to 4 July 2026 along Sterling Way, between numbers 18 and 38. Site workers will assist with deliveries to local businesses as needed.

Parking bays on College Road between Sterling Way and Regal Court will be suspended to facilitate the works between 17 March and 4 July 2026, further information will be provided nearer the time.

Buses

For most of the work, all bus routes will continue to operate as normal, but some journeys may take longer. Customers are advised to allow more time for their journeys. For local trips, walking or cycling may be quicker. Check live updates at: tfl.gov.uk/bus/status.

For the overnight resurfacing work from 29 June to 4 July bus routes 34, 102, 144, 444, 491 and SL1 will be affected. Further information will be provided nearer the time.

Pedestrians

Pedestrian diversion routes will be clearly marked and well-lit throughout the works.

If you have any questions on the works, TfL can be contacted on 0343 222 1234.