Notification of upcoming works - Phase 1

In February 2024, we presented the design for improvements in Enfield Town and a statutory consultation on the proposed changes for Phase 1 was carried out. Following the statutory consultation, a decision was made to implement Phase 1 of the project, and we are now writing to inform you of construction works taking place.


What works will be occurring?

Below is a summary of the interventions being delivered as part of Phase 1:

  • Closure of the eastern end of Little Park Gardens at its junction with Church Street to create a new public square.
  • Changes to how traffic will operate on Little Park Gardens to facilitate the road closure.
  • Changes to how traffic operates at the Church Street / Cecil Road / Little Park Gardens junction (straight ahead from Cecil Road will now be permitted for general traffic) 
  • New signalised crossing at the junction of Church Street / Sarnesfield Road 
  • Relocation of the crossing point on Cecil Road which will also be upgraded to become a signalised toucan crossing. 
  • Implementation of a diagonal path linking the two new crossing points on Church Street / Sarnesfield Road junction and Cecil Road 
  • Changes to waiting and loading within the Phase 1 project area.

Construction will be delivered in a series of stages. To carry out the works in a safe and efficient manner we will need to introduce temporary traffic measures on the junctions and roads mentioned above. These measures will include signage placed over the carriageway and footway, and traffic and pedestrian diversions. This will mean that people driving motor vehicles will have to follow the signed diversion routes and people walking will occasionally walk on the carriageway or the opposite side of the road within designated zones until works are completed. Measures will also include parking restrictions that will be signed in the area. Access to nearby properties will be maintained.

As the works progress, our contractor will be writing to residents and businesses with further information about the construction plan specific to their area, but signage should also be checked as changes may occur should any unforeseen circumstances arise. 

Some works will require full road closures, and diversions will be put in place. This may result in temporary night closures of sections of roads and footways, and any impact will be kept to a minimum. Impacted residents and businesses will be notified separately and signage on site will also be provided.

To enable us to carry out these works we will be using machinery and vehicles that may cause some noise. We will try to keep this to a minimum. 

If you have any queries relating to the construction works, please contact our contractor TKJV on 020 8983 0077 or at etc@riney.co.uk.


When will the works take place?

These works will begin Monday 1 July 2024 and will continue until completion of the works which are estimated to take approximately four months. This timeline may change due to any unforeseen circumstances that arise related to the existing site or works progressing faster than expected.  

How will we manage the impact on residents and businesses?

We recognise that construction works on our streets can cause temporary disruption to those living or working nearby. Please be assured that every effort is made to minimise any unnecessary noise or foot/vehicle traffic disruption, and we have reminded all staff to be considerate to our neighbours. We apologise in advance for any inconvenience that this work may cause.

If you have any questions about this project, please email us at journeysandplaces@enfield.gov.uk. 